Currently Playing: The Walls are Closing In - an update on Kingston's Ferry Dock as new sheet pile is installed 4K

Kingston, Ontario - May 2nd, 2026 a week of very hard work by Soletanche Bachy Canada, and others, has shown considerable progress. Weekend working contributed to this significantly. First falsework - used to guide new pile precisely - is in place at both ends of the extension and work will now proceed quite quickly - and very accurately. This is a longer update than usual - reflecting the unusually busy week. Chapter markers: 00:00 - Monday - A second Terex crane has arrived for assembly 04:47 - Tuesday - the third crane is built 09:20 - Wednesday - first falsework piles are installed 13:22 - Thursday - Falsework well advanced on the east end 16:04 - Friday - Sheet piling begins 18:52 - Saturday - the western falsework begins installation All music is from Epidemic Sound